T O U R E C H A F : S H O R I N G T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M
Special applications
...
26
> Deck for fitting hollow
core slabs:
> Shoring towers on a
tank head:
Prefabrication
of the shoring
tower on the
ground on a
temporary
scaffold before
lifting to a height
of 50 m.
Several towers
placed side by
side below the
beam.
Scaffolding former
reproducing the
shape of the tank
head.
Site
boundary
Tourehaf
Beams
Double
diagonal
braces
Guardrail MDS
Shoring position:
100
70
Moving position:
Screw jacks
down
Anchors
Screw jacks
raised
> Reinforced 1.50 m
overhanging deck and platform
for assembling formwork:
Tourechaf
Mills Pano
Mills Phal
Mills Pano
fillet
> Shoring a rigid frame
bridge using Mills Pano:
Deck at the top of the towers
Same principle
for framework
for an overhang:
> Mobile tower for beam
formwork:
TOURECHAF