T O U R E C H A F : S H O R I N G T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M
Compatibility
with scaffolding...
> Using a safe erection
guardrail for safe
assembly of standard
formwork:
-Where the walls and slabs round
the outside are already fitted with
guardrails;
- and the Tourechaf shoring is fitted
with decks at the top.
>
1
- Fitting 3.50 m high standards
with 0.35 m ledgers for the overhang.
>
2
- Fitting safe erection guardrails
from the deck. Fixing the guardrails
using ledgers.
>
3
- Next to the access to a small
area, fit the main beams, joists and
plywood from the Tourechaf deck.
Continue fitting joists over the whole
area of the formwork.
>
4
- From the panels already laid,
collect the first pack of plywood and
lay the plywood over the joists up to
the guardrail.There should be not
more than 25 cm between beams.
>
5
- Fit the final site guardrails fixed
to the joists.
>
6
- To remove, place the guardrails
on the edge of the slab.
Remove the shoring while standing on
the deck of the towers by unscrewing
the adjustable heads.
Remove the guardrails at the edge of
the formwork, the safe erection
guardrail still being in place.
The formwork components should be
lowered to the ground or placed on
the slab from the edge of the deck.
The towers should be dismantled
according to the instructions.